Allow for price changes without hiding the basis
Separate escalation, exchange exposure, contingency and markup in a transparent construction budget.
Use dated rates
A rate needs a scope, unit, location, date and tax basis. Separate material, labor and equipment so a wage increase does not inadvertently inflate material cost. Record whether delivery, installation and consumables are included.
Separate risk drivers
Material escalation, wage increases, fuel changes and exchange movements affect different portions of cost. Apply each assumption to the relevant exposed amount. Already purchased quantities and fixed-price commitments should not carry the same exposure as unfixed future purchases.
Use explicit exchange multipliers
Keep project currency separate from supplier currency. If a supplier price is in USD and the project is in another currency, multiply by the stated number of project-currency units per USD. Record the rate source and date. A presentation conversion changes displayed totals; explicit cost-basis conversion changes supported monetary inputs separately.
Show what-if results honestly
The scenario tool displays additive direct-cost sensitivities for your chosen horizon. It does not predict prices or attach a statistical confidence level. Contingency covers defined uncertainty; it should not silently duplicate the same escalation or foreign exchange allowance.