Calculate crews, equipment and work duration
Plan from resources to time, or from a target date to the resource demand, using explicit production assumptions.
Productivity needs a measured basis
Production can be expressed as work units per crew-day or equipment-day. Use comparable historical performance or an explicitly stated planning assumption. Actual production = completed quantity / crew-days used. Record conditions when comparing results.
Calculate the bottleneck
Crew output = production per crew-day × crews. Equipment output = capacity per equipment-day × equipment count. Where both control the same operation, the lower output controls duration. Duration = work quantity / controlling daily output.
Plan from a deadline
Required crews = ceiling(quantity / (production per crew-day × target working days)). Workers = crews × workers per crew. This assumes available work fronts and adequate equipment. More resources can cause congestion rather than proportional acceleration.
A programme is more than a sum
Independent activities can overlap. Finish-to-start dependencies and lags establish sequence. Apply a working calendar and separately allow procurement, curing, weather, holidays and access. Programme does not automatically level shared crews or equipment. Use the optional bounded remaining-work leveling in Forecast & completion and review its blocked activities.