Quick Estimate: from benchmark to a detailed project
Prepare an indicative building, pavement, pipeline or earthwork budget without presenting it as a measured bill of quantities.
Choose the correct budget basis
Open Quick Estimate. Use building floor area, pavement area, pipeline length or earthwork volume. Enter your benchmark rate, currency, source, date, scope and exclusions. Building budgets use area per floor and the number of floors; linear and volume budgets use their displayed units.
Show allowances and uncertainty
Review contingency, escalation and the entered low/high range. The range is an assumption, not a statistical confidence interval. Optional budget allocations divide a preliminary budget; they do not measure materials or design a system.
Keep the baseline separate
Save the Quick Estimate before converting it into a detailed project. Conversion retains a comparison baseline and starts detailed activities separately. It does not generate quantities, add the budget twice, or establish structural or MEPF scope.