Actual time-related site overhead calculator
Quantify evidenced incremental site overhead for a delay period using verified daily costs.
Calculation method
Add verified daily time-related costs and multiply by the entered delay days. Where daily costs vary, calculate each period separately and add the subtotals.
Worked example
Thirty days at 4,500 per day gives 135,000 in the entered currency.
Scope and assumptions
Use a consistent currency and day basis. Support the inputs with payroll, timesheets, hire invoices and other records. Exclude one-off costs, direct task costs and amounts recovered elsewhere. The entered delay days require a separate entitlement and causation assessment.