Advance payment recovery scenario calculator

Model recovery from one payment using an entered recovery rate and the outstanding advance balance.

Calculation method

Outstanding advance equals original advance minus prior recoveries. Current recovery is the lesser of outstanding advance and eligible amount multiplied by the recovery rate.

Worked example

Twenty percent of 500,000 is 100,000. If the remaining advance is 70,000, current recovery is capped at 70,000.

Scope and assumptions

Use one currency and apply the contract’s recovery basis, thresholds and timing separately. This models one payment only.