Concrete slab volume calculator
Measure slab concrete from plan dimensions, opening area and uniform thickness.
Calculation method
Net area equals length × width minus deductible opening area. Multiply by thickness in metres, then apply the order allowance.
Worked example
A 12 m × 8 m slab with 6 m² of deductible openings and a 150 mm thickness needs 13.5 m³ net, or 14.175 m³ with 5% allowance.
Scope and assumptions
Use the applicable measurement rules for opening deductions. Beams, thickened areas and reinforcement are measured separately.