Contract budget headroom calculator
Compare a funding limit with the base commitment, approved changes and separate forecast allowances.
Calculation method
Adjust the original commitment for approved additions and omissions. Add pending allowances and reserve, then subtract from the funding limit.
Worked example
A 10,500,000 adjusted commitment plus 900,000 in pending changes and reserve leaves 600,000 against a 12,000,000 limit.
Scope and assumptions
Use one tax and currency basis. Keep the pending forecast and reserve separate from approved amounts.