Dewatering wellpoint quantity calculator

Count positions for identical straight wellpoint runs with an installation point at each end.

Calculation method

Round up run length divided by specified maximum spacing for the interval count, add one end position per run and add spares to the order.

Worked example

Two independent 30 m runs at 1.5 m spacing need 42 installed points and 44 assemblies including two spares.

Scope and assumptions

Use approved runs and spacing. Shared end points must be counted only once. Pump capacity and drawdown require separate assessment.