Calculation method

Bank cut = length × width × average depth. Reuse = the lesser of available bank cut and compacted fill divided by yield. Loose export = remaining bank cut × bulking factor. Truckloads round up.

Worked example

The sample produces 90 m³ of bank cut, 112.5 m³ of loose export and 12 truckloads.

Scope and assumptions

Assumes suitable cut material is reused first. Verify suitability, survey quantities, moisture, truck payload and disposal restrictions separately. Workspace transfer is available for excavation-only runs with zero fill.