Eichleay formula calculator
Allocate fixed company-wide overhead by billings and estimate unabsorbed home-office overhead for entered delay days.
Calculation method
Divide project billings by total company billings and apply that share to company fixed home-office overhead. Divide allocated overhead by actual performance days and multiply by the entered delay days.
Worked example
Project billings of 5,000,000 out of 25,000,000 allocate 500,000 of 2,500,000 fixed overhead. At 500 performance days and 40 delay days, the formula gives 40,000.
Scope and assumptions
Use the same actual performance period and accounting basis for all amounts. This U.S. federal contracting method has fact-specific eligibility requirements. Assess entitlement separately. Hudson, Emden and Eichleay are alternative methods for the same overhead exposure.