TrendyBuilders logoTrendyBuilders
Open workspace ↗
← Engineering Calculators

Emden formula calculator

Model head-office overhead and profit using the contractor’s actual accounts-based percentage.

Calculation method

Multiply the contract sum by the actual accounts-based head-office overhead and profit percentage. Divide by the original contract period and multiply by the entered delay days.

Worked example

A 10,000,000 contract, 8% actual allowance and 400-day original period give 2,000 per day and 80,000 for 40 days.

Scope and assumptions

Use a percentage supported by the contractor’s accounts for a representative period. Verify the calculation basis, method applicability and recoverability of any profit element separately.

SCL Delay and Disruption Protocol, 2nd edition