Equipment output and duration calculator
Estimate working duration from planned output and available operating hours.
Calculation method
Daily output = hourly output × machines × scheduled hours × productive share. Divide quantity by daily output and round up for whole working days.
Worked example
Two machines at 40 units/hour, eight hours/day and 75% productive time deliver 480 units/day. A 2,400-unit activity takes five working days.
Scope and assumptions
Use the same work unit for quantity and output. Assumes parallel operation at a constant rate. Mobilization, sequencing and access constraints are separate.