Estimate cost variance calculator

Compare a forecast with a baseline budget and calculate the difference in amount and percent.

Calculation method

Subtract baseline from forecast. Divide the difference by baseline and multiply by 100 for the percentage variance.

Worked example

A forecast of 1,080,000 against a baseline of 1,000,000 is 80,000 over budget, or 8%.

Scope and assumptions

Compare the same scope, currency, tax basis and price date. A positive result means the forecast exceeds the baseline.