Forecast cost at completion calculator

Combine actual cost and remaining forecast costs to estimate the final cost and budget overrun or underrun.

Calculation method

Add remaining committed and uncommitted costs to get cost to complete. Add actual cost to get the forecast at completion. Subtract the approved budget from the forecast.

Worked example

Actual cost of 5,800,000 plus 6,500,000 to complete gives a final forecast of 12,300,000, which is 300,000 over a 12,000,000 budget.

Scope and assumptions

Use one cut-off date and currency. Exclude costs already included in the actuals from the remaining commitments. Add remaining risk allowances to the uncommitted forecast where applicable.