Foundation blinding concrete calculator
Estimate lean concrete for uniform rectangular blinding pads with an edge extension.
Calculation method
Add twice the edge extension to each plan dimension. Multiply by thickness in metres and pad count. Apply the order allowance to net volume.
Worked example
Ten 2 m × 1.5 m pads with 100 mm extensions and 75 mm blinding require 2.805 m³ net.
Scope and assumptions
Assumes separate, identical rectangular pads. Measure shared or irregular blinding separately and use specified dimensions.