Foundation drain pipe and cleanouts calculator

Estimate stock lengths and scheduled cleanouts for separate identical foundation drain runs.

Calculation method

Apply allowance to each run, then round up the stock-piece count for that run. Multiply the piece and cleanout counts by the number of runs.

Worked example

Three 26 m runs with 5% allowance require 15 six-metre stock pieces and six cleanouts.

Scope and assumptions

Assumes offcuts stay within each individual run. Use the approved route and cleanout schedule. Price fittings, bedding and filter layers separately.