Foundation excavation with working space calculator
Measure in-place excavation volume for identical rectangular pits with vertical sides.
Calculation method
Add twice the working space to each foundation plan dimension. Multiply the resulting pit area by excavation depth and pit count.
Worked example
Six 3 m × 2 m foundations with 0.5 m working space on each side and 1.8 m excavation depth require 21.6 m³ per pit, or 129.6 m³ in total.
Scope and assumptions
Use the excavation dimensions and working space shown on the approved drawings. Measure batters, benches, ramps and changes in depth separately.