Gabion basket fill quantity calculator

Estimate in-place rock fill volume and procurement tonnage for identical rectangular gabion baskets.

Calculation method

Multiply basket dimensions by basket count. Multiply volume by in-basket bulk density, then apply the rock allowance to the estimated mass.

Worked example

Twenty-five 2 m × 1 m × 0.5 m baskets hold 25 m³. At 1.7 t/m³ and 5% allowance, the order is 44.625 t.

Scope and assumptions

Use a bulk density that includes voids between placed stones. Measure baskets of different sizes in separate runs.