Headed shear stud quantity calculator
Convert scheduled headed shear studs into a purchased count for identical composite beams.
Calculation method
Multiply the scheduled count by beam count, add spares and round up to a full purchase pack.
Worked example
Twelve beams with 24 studs each plus 12 spares require 12 packs of 25.
Scope and assumptions
Use the approved stud schedule for one stud type. Welding, inspection and testing are separate allowances.