Hudson formula calculator

Model head-office overhead and profit using the tender allowance percentage.

Calculation method

Multiply the contract sum by the tender head-office overhead and profit percentage. Divide by the original contract period and multiply by the entered delay days.

Worked example

A 10,000,000 contract, 10% tender allowance and 400-day original period give 2,500 per day and 100,000 for 40 days.

Scope and assumptions

This is a tender-based scenario. Verify whether the method and profit element are appropriate for the contract and governing law. Check for overlap with amounts recovered elsewhere.

SCL Delay and Disruption Protocol, 2nd edition