Hudson formula calculator
Model head-office overhead and profit using the tender allowance percentage.
Calculation method
Multiply the contract sum by the tender head-office overhead and profit percentage. Divide by the original contract period and multiply by the entered delay days.
Worked example
A 10,000,000 contract, 10% tender allowance and 400-day original period give 2,500 per day and 100,000 for 40 days.
Scope and assumptions
This is a tender-based scenario. Verify whether the method and profit element are appropriate for the contract and governing law. Check for overlap with amounts recovered elsewhere.