Labor crew duration calculator
Estimate paid labor-hours and working days from productivity, crew size and productive time.
Calculation method
Productive labor-hours = quantity ÷ output per productive hour. Divide by productive share for paid labor-hours, then divide by crew paid hours per day for working days.
Worked example
A 1,200-unit task at three units per productive labor-hour takes 500 paid labor-hours at 80% productive time. Five workers on eight-hour days complete it in 12.5 working days.
Scope and assumptions
Use a consistent work unit and comparable productivity. Does not model dependencies, shift restrictions or crew learning. Paid hours are proportional before rounding days.