Pavement layer quantities calculator
Calculate concrete order volume and granular subbase quantities from specified thicknesses.
Calculation method
Area = length × width. Concrete order volume = area × concrete thickness × (1 + allowance ÷ 100). Loose subbase = area × compacted thickness × loose-to-compacted factor.
Worked example
The sample produces 600 m² of pavement, 126 m³ of concrete to order and 108 m³ of loose subbase.
Scope and assumptions
Use thicknesses from the project design. Quantities cover a uniform rectangular section. Joints, dowels, drainage and earthwork are separate.