Pile concrete overbreak calculator
Compare actual placed concrete with the theoretical volume of a pile or a group of identical piles.
Calculation method
Multiply the nominal circular area by the concreted length and pile count. Compare measured placed volume with the theoretical total in cubic metres and as a percentage.
Worked example
Five 0.8 m diameter piles with 10 m concreted length each require 25.133 m³ theoretically. Placing 28 m³ gives a variance of +2.867 m³, or +11.41%.
Scope and assumptions
Use concrete actually placed. Exclude returned loads, pump priming and rejected concrete. A variance alone cannot identify the cause or establish pile integrity.