Pile test allowance calculator
Calculate the budget quantity for one test type from a project-specified sampling percentage and minimum count.
Calculation method
Round up the percentage of eligible piles and use the larger of that count and the specified minimum.
Worked example
For 80 eligible piles with a 5% sampling rate and a two-test minimum, allow four tests.
Scope and assumptions
This applies user-entered requirements to one lot and one test type. Use the contract or testing schedule to specify the sampling rules, including any individual test locations.