Piling platform aggregate calculator
Estimate compacted volume and loose aggregate quantities for a rectangular piling working platform.
Calculation method
Multiply platform area by thickness for compacted volume. Multiply by the loose-to-compacted factor for delivered volume and by loose bulk density for delivered mass.
Worked example
A 40 m × 15 m platform at 0.4 m thickness needs 240 m³ compacted. The given factor and density give 288 m³ loose and 475.2 t.
Scope and assumptions
Use dimensions from the working platform design and confirm the factor and loose bulk density with the supplier. Quantify ramps, edge extensions and variable-depth zones separately.