Tapered topping concrete calculator

Estimate concrete for floor topping with a uniform width and linearly varying thickness.

Calculation method

Average the two end thicknesses, multiply by plan area and zone count, then apply order allowance.

Worked example

Three 8 × 5 m zones tapering from 50 to 90 mm require 8.4 m³ net and 8.82 m³ with 5% allowance.

Scope and assumptions

Use zones with a uniform width and a single linear taper. Split irregular areas and separately measure openings or local deepenings.