Tapered topping concrete calculator
Estimate concrete for floor topping with a uniform width and linearly varying thickness.
Calculation method
Average the two end thicknesses, multiply by plan area and zone count, then apply order allowance.
Worked example
Three 8 × 5 m zones tapering from 50 to 90 mm require 8.4 m³ net and 8.82 m³ with 5% allowance.
Scope and assumptions
Use zones with a uniform width and a single linear taper. Split irregular areas and separately measure openings or local deepenings.