Progress payment reconciliation calculator

Reconcile current and previous cumulative certificate values and calculate the net amount for the current period.

Calculation method

Subtract the previous cumulative gross value from the current one. Add current-period credits and subtract current-period deductions.

Worked example

Cumulative gross value increases from 1,800,000 to 2,500,000. Deducting 90,000 and adding 15,000 gives a current net value of 625,000.

Scope and assumptions

Use one currency and a consistent tax basis. Enter only incremental deductions and credits that are outside the gross figures. A negative result indicates a net adjustment for review.