TrendyBuilders logoTrendyBuilders
Open workspace ↗
← Engineering Calculators

Prolongation cost scenario calculator

Model time-related costs from entered days, daily costs and adjustments.

Calculation method

Time-related cost = days × combined daily costs. Scenario total = time-related cost + other incremental cost − savings and recoveries.

Worked example

Thirty days at 4,500 per day, plus 10,000 and less 5,000, gives 140,000 in the entered currency.

Scope and assumptions

Use one currency and the same day basis for all rates. Enter only incremental costs and avoid double-counting. Assess contractual entitlement, causation and evidence separately.