Soil nail grout quantity calculator
Estimate theoretical annular grout and order allowance for identical fully grouted soil nails.
Calculation method
Use the bore area less the solid bar area. Multiply by scheduled grouted length and count, then apply the grout allowance.
Worked example
Twenty 6 m nails in 100 mm bores with 25 mm bars need about 0.884 m³ net and 1.016 m³ with a 15% allowance.
Scope and assumptions
For a uniform circular bore and solid round nail. Actual grout take depends on ground conditions and site records. Use dimensions from the approved design.