Strip footing concrete calculator

Calculate concrete volume along a uniform strip footing.

Calculation method

Multiply measured strip length by width and thickness, then apply the order allowance.

Worked example

A 45 m strip, 0.6 m wide and 0.3 m thick, needs 8.1 m³ net or 8.505 m³ with 5% allowance.

Scope and assumptions

Use drawing dimensions and lengths adjusted for overlapping junctions. Measure stepped sections separately. Excavation and reinforcement are separate.