Unit rate build-up calculator
Build a unit rate from batch costs for materials, labor, equipment and subcontract work.
Calculation method
Add all batch direct costs and divide by batch quantity. Apply the entered markup to the direct unit rate.
Worked example
Direct costs of 50,000 spread over 100 units give 500 per unit. A 10% markup gives 550 per unit.
Scope and assumptions
Use one currency and price basis. Avoid duplicating costs carried in subcontract prices. Model taxes and separate or compounded markups in the project estimate.